Math questions are free points on the plumbing exam if you are ready for them, and a time sink if you are not. Offsets, fall over a run, pressure from elevation, and simple takeoffs all show up.

Grab a calculator and a scratch sheet. Try to work each one out before you look at the answers. The explanations show the steps, so you can see exactly where a wrong answer came from.

  1. Question 1 of 15

    A sump holds 10 cu ft of water. Using 7.48 gal per cu ft and 8.35 lb per gal, what does that water weigh, to the nearest pound?

    Show answerHide answer

    Answer: A. 625 lb

    10 cu ft × 7.48 = 74.8 gal, and 74.8 × 8.35 = 624.6 lb, rounding to 625 lb. The 84 lb answer adds the two constants instead of applying them in sequence. Watching the units confirms the order: cubic feet times gallons-per-cubic-foot leaves gallons, and gallons times pounds-per-gallon leaves pounds.

  2. Question 2 of 15

    A rolling offset has a true offset of 10.0 in. and is made with 45 degree fittings. Using a multiplier of 1.414, what is the travel?

    Show answerHide answer

    Answer: A. 14.1 in.

    10.0 x 1.414 = 14.14, or 14.1 in. The rolling part of the problem is finished once the true offset is known, and from there nothing is different from a simple offset. That is the whole method: combine the two displacements into one, then apply the multiplier.

  3. Question 3 of 15

    A job costs $880.00. The contractor applies a 25 percent markup on cost. What is the selling price?

    Show answerHide answer

    Answer: D. $1,100.00

    Markup is figured on cost: 25 percent of $880 is $220, so the price is $1,100.00. The $1,173.33 answer is what a 25 percent margin would produce, and it appears here deliberately because the two calculations are constantly confused. The $905 answer adds 25 dollars rather than 25 percent.

  4. Question 4 of 15

    A 180 gal tank must be filled in 15 minutes. What flow rate is required?

    Show answerHide answer

    Answer: C. 12 gpm

    180 / 15 = 12 gpm. This is the same relationship as the previous two questions rearranged for the third unknown. Once rate times time equals volume is fixed, any one of the three can be found from the other two, and the units confirm which operation applies.

  5. Question 5 of 15

    A drain starts at invert elevation 102.40 ft and ends at 101.20 ft over a run of 80 ft. What is the slope in inches per foot?

    Show answerHide answer

    Answer: B. 0.18 in. per ft

    The fall is 102.40 - 101.20 = 1.20 ft, which is 14.4 in. Dividing by the 80 ft run gives 0.18 in. per ft. The 0.015 answer skips the conversion to inches and reports feet per foot, which is a real quantity but not what was asked. Converting before dividing is what keeps the units straight.

  6. Question 6 of 15

    A tank holds 24 cu ft of water. Using 7.48 gal per cu ft, what is its capacity in gallons, to the nearest gallon?

    Show answerHide answer

    Answer: A. 180 gal

    24 × 7.48 = 179.5, which rounds to 180 gal. The 3 gal answer comes from dividing by 7.48 instead of multiplying, and a moment's thought rules it out: a cubic foot is bigger than a gallon, so the number of gallons must be larger than the number of cubic feet, not smaller.

  7. Question 7 of 15

    A pipe must move 9 in. in one direction and 12 in. perpendicular to it. What is the direct diagonal distance between start and finish?

    Show answerHide answer

    Answer: B. 15.0 in.

    The square root of 9 squared plus 12 squared is the square root of 225, which is 15.0 in. This is the 3-4-5 triangle scaled by three, and recognising it saves time. Choosing 21.0 adds the legs, which is always too long: the diagonal is shorter than going around two sides.

  8. Question 8 of 15

    A backhoe rents for $350 per day and its operator costs $65 per hour. The machine is used for three 8-hour days. What is the total equipment charge?

    Show answerHide answer

    Answer: C. $2,610

    Rental is 3 x $350 = $1,050. The operator works 8 hours a day for three days, so 24 hours at $65 = $1,560. Together that is $2,610. The two wrong figures are each half the answer: $1,050 counts only the machine, $1,560 only the operator. Equipment on a job almost always carries both.

  9. Question 9 of 15

    A supply delivers 72 psi. The highest fixture is 45 ft above it and friction loss along the run is 11 psi. Using 0.434 psi per ft, what pressure remains at that fixture?

    Show answerHide answer

    Answer: D. 41.5 psi

    Elevation loss is 45 x 0.434 = 19.53 psi. Subtracting both: 72 - 19.53 - 11 = 41.5 psi. The 52.5 answer omits the friction loss and the 61.0 answer omits the elevation, so each drops one term. The 16.0 answer subtracts 45 psi for elevation, treating each foot as a full psi, which is the error that makes workable systems look impossible on paper.

  10. Question 10 of 15

    The downstream invert of a drain is at elevation 96.25 ft. The run falls 0.75 ft. What is the upstream invert elevation?

    Show answerHide answer

    Answer: A. 97.00 ft

    96.25 + 0.75 = 97.00 ft. Going upstream reverses the operation, and this is deliberately paired with the previous question so that the direction has to be decided rather than assumed. Choosing 95.50 subtracts out of habit and puts the upstream end below the downstream one.

  11. Question 11 of 15

    A container holds 462 cu in. of water. Using 231 cu in. per gal, what is that in gallons?

    Show answerHide answer

    Answer: D. 2 gal

    462 ÷ 231 = 2 gal. This conversion runs the opposite way from cubic feet to gallons: a cubic inch is much smaller than a gallon, so here you divide. Checking which unit is larger before deciding whether to multiply or divide prevents most errors of this type.

  12. Question 12 of 15

    A plumber needs a 12 in. offset and cuts pipe for a travel of 24 in. using 45 degree fittings. The finished offset measures about 17 in. What went wrong?

    Show answerHide answer

    Answer: B. The 30 degree multiplier of 2.000 was used instead of the 45 degree multiplier

    A travel of 24 in. for a 12 in. offset implies a multiplier of 2.000, which is the 30 degree figure. Fitted with 45 degree fittings, that travel produces an offset of 24 / 1.414 = 17 in., matching what was measured. Using the constant for the wrong fitting angle is the spec's other named trap, and it shows up as an offset that overshoots rather than as pipe that will not seat.

  13. Question 13 of 15

    A job needs 200 ft of copper at 8 percent waste and 150 ft of PVC at 12 percent waste. What quantities should be priced?

    Show answerHide answer

    Answer: A. 216 ft copper and 168 ft PVC

    Copper: 200 x 1.08 = 216 ft. PVC: 150 x 1.12 = 168 ft. Each material carries its own percentage and they are applied separately. Using one blanket figure for both is the error this targets, because waste differs by material and by how it is cut: rigid copper offcuts and PVC offcuts do not behave the same way.

  14. Question 14 of 15

    Using 1 psi = 2.30 ft of head, how high a column of water does 60 psi support?

    Show answerHide answer

    Answer: A. 138 ft

    60 x 2.30 = 138 ft. The 26 ft answer divides by 2.30 instead of multiplying, and a quick check rules it out: since one psi lifts more than two feet of water, sixty psi must lift well over a hundred feet, not a quarter of that.

  15. Question 15 of 15

    A building sewer must connect to a main whose invert is at elevation 94.60 ft. The run is 80 ft at 1/8 in. per ft. What invert elevation is needed where the sewer leaves the building?

    Show answerHide answer

    Answer: B. 95.43 ft

    The fall is 80 x 0.125 = 10 in., which is 0.83 ft. Working upstream from the fixed connection: 94.60 + 0.83 = 95.43 ft. This is the everyday form of the problem, because the connection elevation is fixed and the building end is what must be established. Choosing 93.77 subtracts, which would run the sewer uphill toward the main.

0 / 15Answer the questions above to see your score

Most math misses come from units, not the formula. Inches vs feet and fractions vs decimals cause more wrong answers than anything else.

If a question took you more than two minutes, practice that type until it is fast. Speed on math buys you time for the code questions.